University of Manchester  –  Chemistry Building

In 2022 William Bailey Ltd were appointed by the University of Manchester to undertake a full refurbishment of 2No floors, Levels 4 + 5, including the full replacement of all mechanical services infrastructure services (Basement, Roof and Risers).

Levels 4 & 5 consists of newly refurbished laboratory areas, teaching spaces and Write up areas for students and academics to carry out specific laboratory tests as well as a full refurbishment of the toilet and plantroom areas.

Phase 3 of the works which is Level 1 commenced January 2025 and was completed August 2025

The works consisted of:-

  • Supply air Ventilation
  • Fume extract Ventilation
  • LTHW Heating
  • Process Cooling Water
  • Fume Cupboards and Lab pressure control
  • Domestic Hot and Cold Water Services
  • Metering Stations/Strategy
  • Specialist Gases
  • Gas monitoring
  • Fire Suppression to Gas Rooms
  • Building Management System
  • Vulcathene drainage

Phase 2 of the works which are Levels 2 & 3 commenced September 2023 and was completed September 2024.

Works commenced on Dover Street site September 2025 and are expected to be completed August 2026.